Administration Building HVAC Renewal Project - In Progress

The Administration Building HVAC Renewal project will retrofit existing HVAC and critical infrastructure components within the building.

 

Construction on the project began May 19, 2025.

Project updates:

  • May 19 - June 30
    • Air conditioning will be shut off beginning May 21st.
      • Air filtration and air changes will continue as normal, however conditioned (cooled) air will not be available.
  • June 30 – August 4
    The Administration Building will be unoccupiable during this period, with the exception of Cougar Central, which will remain open and operational.
  • Now through June 27
    The Campus Moves team is actively relocating Administration Building occupants to UVA.
    For questions related to moves, please contact the Campus Moves team.
  • For any Project-specific inquiries please contact project manager.

Administration Building HVAC - Heat Illness Prevention Fact Sheet

Resources

Project Manager: 

Ian Irvine

Projected Project Cost: 

$12,478,380

Funding Source: 

 

Completed: 

Est. 02/12/26